CASE STUDIES
|
CLIENT: BiState Agency & NYC
Consulting Firm
PROJECT TYPE: Sediment Characterization
DESCRIPTION: Sediment samples
were characterized for disposal options according to “the management and regulation
of dredging activities and dredged material in New Jersey’s tidal water, October
1997” via bulk chemistry and leachate methods.
--------------------------------------------------------------------------------
CLIENT: Top Twenty Environmental
Consulting Firm
PROJECT TYPE: Fast Track site characterization
DESCRIPTION: 10-20 samples
were received each evening for TCL/TAL analysis on a 72 HR fax, one week hardcopy
TAT. The project lasted for 7 days and was successfully completed. The quick TAT
facilitated the property transaction and additional contracts have been obtained
with the final client.
--------------------------------------------------------------------------------
CLIENT: National Consulting
Company
PROJECT TYPE: Site Characterization
DESCRIPTION: 100’s of soil,
sediment, water, and fish samples were analyzed for TAL/TCL parameters. Results
were provided in a full validation type package and Delimited ASCII Diskette Deliverable.
--------------------------------------------------------------------------------
CLIENT: National Consulting
Company
PROJECT TYPE: Plume Delineation
DESCRIPTION: Veritech provided
3 hour TAT on TCL Volatile Analysis to direct two Geoprobes during plume delineation
project. Samples were collected each morning and afternoon; the plume was delineated
in a week.
--------------------------------------------------------------------------------
CLIENT: BiState Agency
PROJECT TYPE: Call in Support
DESCRIPTION: Veritech analyzed
1000’s of samples in support of investigation & remediation projects. Analyses were
typically quick TAT work on heavily contaminated soils and sediments. Field sampling
support was also provided.
--------------------------------------------------------------------------------
CLIENT: National Insurance
Company
PROJECT TYPE: Home Heating Oil Replacement
DESCRIPTION: 1000’s of samples
were received from numerous contractors for soil characterization of UST parameters.
All TPH samples were performed on TAT of 48 hrs. and VOA samples on a TAT of 72
hours.
--------------------------------------------------------------------------------
CLIENT: Environmental Engineering
Firm
PROJECT TYPE: Lead in Drinking Water Analyses
DESCRIPTION: Project required
analysis of over four hundred drinking water taps on a military base. The samples
had to be analyzed within a two-week period with diskette deliverables provided.
The project was completed ahead of schedule and has shown numerous lead contaminated
locations.
--------------------------------------------------------------------------------
CLIENT: Fortune 100 Lighting
Company
PROJECT TYPE: Plant Decontamination and Closure Analyses
DESCRIPTION: Two-year project
involving analyses for interior decontamination of a large fluorescent light manufacturing
facility. Expedited turnarounds for approximately three thousand inorganic samples
were normal over lifetime of the project. The site was successfully decontaminated
and sold within six months of project completion.
--------------------------------------------------------------------------------
CLIENT: Environmental Engineering
Firm
PROJECT TYPE: Analyses of Soils and Waters for Fortune 500
Site Remediation
DESCRIPTION: Veritech performed priority pollutant metals on
approximately two hundred samples (soils and waters) for a major manufacturer of
specialty metals. The project required development of analytical methods for cerium
and samarium. The soil and water samples were taken to support a plant closure and
sale. The project was successfully completed after one and a half years.
--------------------------------------------------------------------------------
CLIENT: Construction Company
(DOT Project)
PROJECT TYPE: Waste characterization of Soils for DOT Road
Project.
DESCRIPTION: Major roadway
construction required massive soil disposal. Client needed approximately one hundred
waste classification samples analyzed in a one-month period. Analysis of the samples
were performed on time allowing the client to remain on schedule with road construction.
--------------------------------------------------------------------------------
CLIENT: Federal Government
PROJECT TYPE: Characterization of Drinking Water Samples
DESCRIPTION: 100 drinking water
samples were received over a two-month period for complete investigation of potential
hazards. Standard 500 series methods (524.2, 525.2, 515.2, 505, 551, 552) were performed
by Veritech and non-standard common methods were subcontracted and coordinated by
Veritech.
--------------------------------------------------------------------------------
CLIENT: Remedial Contractor
PROJECT TYPE: Building Decommissioning
DESCRIPTION: Over 800 wipe
samples were analyzed for Base/Neutral constituents. The turnaround time was 36
hours after sample received. Samples arrived in batches of 10-90 six days per week.
--------------------------------------------------------------------------------
CLIENT: Environmental Remediation
Firm
PROJECT TYPE: Hazardous Characteristics Screening of Unknowns
DESCRIPTION: In order to support
a long- term contract for disposal of unknown chemicals at a Fortune 100 pharmaceutical
company, Veritech developed qualitative tests specific to the incineration facilities
profile sheet. More than three thousand samples were analyzed over a two-year period.
Using the developed methods enabled the client to dispose of fifty percent more
unknowns than the previous contract winner and at less cost.
--------------------------------------------------------------------------------
CLIENT: Federal Government
(DOD)
PROJECT TYPE: Waste Characterization of Stockpiled Soil
DESCRIPTION: Stockpiled soils
from numerous remediation projects at DOD research facility required waste characterization
for disposal. Approximately fifty samples had to be analyzed in a one-month period
and reported with full regulatory deliverables as per DOD specifications. The project
was completed on schedule.
--------------------------------------------------------------------------------
CLIENT: Federal Government
(DOD)
PROJECT TYPE: Identification of unknown samples
DESCRIPTION: Storage building
for DOD research facility required absolute identification of over 2500 samples
in a three-month time frame. The project was completed within the required period
by utilizing a combination of Fourier Transform Infrared Spectroscopy, X Ray Fluorescence
Spectroscopy, and X Ray diffraction. Based upon the absolute identifications, no
priority pollutant scans were necessary and the ultimate savings to the government
was in excess of $ 2,000,000.
--------------------------------------------------------------------------------
CLIENT: Fortune 100 Electronics
Company
PROJECT TYPE: Mercury Analysis of Soil and Water samples
DESCRIPTION: Natural disaster
caused collapse of warehouse. The building was extensively stocked with items containing
elemental mercury. Snow and spring rains threatened to carry the contamination off-site.
An emergency clean-up effort was commenced and hundreds of emergency soil and water
samples were analyzed for mercury. The contamination was successfully contained
on-site in part to the timeliness of the mercury analyses.
--------------------------------------------------------------------------------
CLIENT: Major Consultant/US
Army Corps of Engineers
PROJECT TYPE: TCL/TAL Analysis
DESCRIPTION: Investigation and delineation of contaminants at
a NJ Superfund site. 100s of samples were received for TCL/TAL and Herbicide analysis.
Data was performed according to the Shell Document specifications and validated
by Army Corps personnel.
|
|
|
 |
 |
 |
 |
|
|